Timeline for HLC Criterion Committee work
End Spring 2018
All criterion committee members understand subcriteria and have begun filling in summary statements and collecting evidence on at least one subcriteron.
All criterion committees have 2018-2019 work plan in place.
Summer 2018
Feedback from HLC co-chairs on summary statement(s).
Spring 2019
Complete and submit Final Quality Initiative Report to HLC no later than March 1, 2019
End Spring 2019
Full drafts of criterion committee assurance statements complete.
Summer 2019
Review of assurance statements; feedback to co-chairs.
Throughout Fall 2019
Committees edit, revise their assurance statements.
October 2019
HLC retreat to review assurance argument as a whole.
March 2020
Final drafts complete and distributed to steering committee.
March 2020
Library evidence spreadsheet and cataloging framework complete; create cover sheets.
Spring 2020
Final review of HLC assumed practices to ensure 100% compliance.
Summer 2020
Final editing of assurance statement by steering committee / those selected to “put into one voice.” Organize/compile final evidence documentation.
Spring/Summer 2020
Editing of document; solicit consultant feedback.
Fall 2020
Begin to upload argument into assurance system; check all links/evidence.
Fall 2020
All evidence compiled.
Fall 2020
Message to campus from President Nook.
Fall 2020
UR roll out of HLC marketing campaign.
Fall 2020
Solicit campus wide feedback on assurance argument (via password protected website as well as meeting with key campus groups).
Fall 2020
Celebration of committee work.
Submit Federal Compliance filing.
January 2021
Student Opinion Survey (HLC will send notification of specific dates from when the link should be shared with students).
February 2021
Student survey distributed and open for 10 days.
March 1, 2021
Assurance system lock date.
March 29-30, 2021
HLC Site Visit .